Coca-Cola Bottling Plant Access Platform Design and Installation

Coca-Cola required a safe way to reach the top of these mixing tanks in the mixing room of their bottling plant. Yale Mechanical determined that a stainless-steel platform was the best way to reliably and safely provide the access they needed.

The platform above the tanks is surrounded by a guard rail and connected to ground level by a staircase, also complete with a handrail. The staircase and platform allow workers to access the tanks as well as piping running along the ceiling for safe and easy maintenance.

BNSF

Yale Mechanical recently completed a major project at BNSF that involved the removal and replacement of a wheel lathe, which is used to true-up wheels on a locomotive. Our millwright team disassembled and removed the old equipment, then replaced the old foundation and support steel before finally unloading, setting and aligning the 60,000-lb piece of new equipment.